PROJECT: MERCED BEACON
scope of work
For this large tank removal, Triton's scope of work included:

- Permitting; site health and safety plan
- Excavate and remove two 10,000-gallon and one 12,000-gallon USTs
- Inert the tanks and haul for disposal
- Communicate with client and local regulatory agency
- Backfill and resurfacing